Project Updates

August 1, 2023 – August 31, 2023

Completion of drainage connections in The Knoll. Completion of burial fill placement. Paving of J North walkways. Irrigation system start-up.

July 1, 2023 – July 30, 2023

Retaining wall completion. Continued screening of burial fill. Removal of trees near C North. Irrigation and electrical pipe placement in J North. Additional trenching for electrical piping in The Knoll. Installation of the liner system for The Knoll Lagoon and Water Feature.

June 2, 2023 – June 30, 2023

Retaining wall installation and soil backfill.

May 30, 2023 – July 15, 2023

Soil material processing and placement for the J North area.

May 30, 2023 – June 23, 2023

Final subgrade material processing and placement for the Knoll area.

May 22, 2023 – July 28, 2023​

Linear and basin water feature construction, including rock delivery.

May 15, 2023 – May 26, 2023​

Misc. ledge cleaning, tree and stump removal. 

April 18, 2023 – June 2, 2023​

Site wall subgrade prep and wall installation. Grading and prep for topsoil areas. Gravel prep for roadways.  

April 10, 2023 – May 5, 2023

Soil screening and processing.

April 10, 2023 – April 28, 2023

Drainage structure and piping installation.

March 24, 2023 – April 15, 2023

Rock processing and burial soil placement.
As the weather warms, the field team will visually monitor the potential dust generated from rock processing and soil placement activities. When required, dust will be mitigated by watering down the soil via water trucks.

March 24, 2023

Ledge removal by hoe-ramming, will be completed on Friday, March 24th.

February 6, 2023 – March 17, 2023

Ledge removal by hoe-ramming, exact duration to be provided in an email notification.
The Cemetery has completed the survey of the existing conditions and will begin removing ledge the week of February 6th. The ledge removal will be performed by hoe-ramming, removal by blasting (rock removal by explosives) will not be required. During this time, neighbors can expect to hear repeated hammering from pneumatic equipment. As a courtesy, the contractor will delay the start of hoe ramming in the morning until approximately 8:30 AM and will conclude these activities by 3 PM.

January 20 – February 3, 2023

Soil screening and processing. Ledge survey and site assessment.

January 5 – 20, 2023

Excavation, soil stockpiling, and earthwork.

December 19 – January 4, 2023

Stripping of topsoil, excavation, and soil stockpiling.

November 28 – December 16, 2022

Vegetation removal, stump clearing, and grinding.

November 7 – 22, 2022

Tree removal and clearing.

September 22, 2022

Newton Cemetery and the Board of Trustees held the third Knoll Development neighbor meeting virtually.
Power Point Presentation

June 13, 2022

Newton Cemetery and the Board of Trustees held the second Knoll Development neighbor meeting virtually.
Power Point Presentation

March 22, 2022

Newton Cemetery and the Board of Trustees held the first Knoll Development meeting at the Chapel building. The meeting was attended by neighbors and City Councilors from Ward 2 and 6.